(单选题)

The()provides the project manager with the authority to apply organizational resources to project activities.

Aproject management plan

Bcontract

Cproject human resource plan

Dproject charter

正确答案

来源:www.examk.com

答案解析

项目章程(project charter)为项目经理使用组织资源进行项目活动提供了授权。

相似试题

  • (单选题)

    The length of the IPv6 address is ( ).

    答案解析

  • (单选题)

    () is one of the quality planning outputs.

    答案解析

  • (单选题)

    The() defines the phases that connect the beginning of a project to its end.

    答案解析

  • (单选题)

    The inputs of developing project management plan do not include()

    答案解析

  • (单选题)

    In approximating costs, the estimator considers the possible causes of variation of the cost estimates, including() .

    答案解析

  • (单选题)

    The () describes, in detail, the project's deliverables and the work required to create those deliverables.

    答案解析

  • (单选题)

    Which of the following statement related to PMO is not correct?()

    答案解析

  • (单选题)

    The()process analyzes the effect of risk events and assigns a numerical rating to those risks.

    答案解析

  • (单选题)

    ()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.

    答案解析

快考试在线搜题