(单选题)

Which of the following statement related to PMO is not correct?()

AThe specific form, function, and structure of a PMO are dependent upon the needs of the organization that it supports.

BOne of the key features of a PMO is managing shared resources across all projects administered by the PMO.

CThe PMO focuses on the specified project objectives.

DThe PMO optimizes the use of shared organizational resources across all projects.

正确答案

来源:www.examk.com

答案解析

中文解释:在下列各项中,有关PMO的说法错误的是 A.PMO的具体形式、职能和结构取决于它支持的组织的需求 B.PMO的关键特征之一是在所有PMO管理的项目之间共享和协调资源 C.PMO关注于特定的项目目标 D.PMO对所管理的所有项目共享资源的使用进行优化