(单选题)
()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.
APlanned value
BEarned value
CActual cost
DCost variance
正确答案
答案解析
略
APlanned value
BEarned value
CActual cost
DCost variance